January 12, 2010
Tue
8:00 am - 12:00 pm
4 hr
Dagupan City, Calasiao, and Sta. Barbara: All areas
Interruption by NGCP to facilitate connection of critical hotspot on
terminal pads of breakers.

January 18, 2010
Mon
10:00 am - 12:00 nn
2 hr
Dagupan City: Carael (Sitio Talaib only)
Primary line revamp.

January 26, 2010
Thu
9:00 am - 12:00 nn
3 hr
Dagupan City: Caranglaan (St. Michael Subdivision only)
Primary line extensions.

February 10, 2010
Wed
9:00 am - 10:00 am
1 hr
Calasiao: Songkoy and Buenlag (Merryland Subdivision only)
Primary line extensions.

February 10, 2010
Wed
10:00 am - 12:00 nn
2 hr
Calasiao: Buenlag (Sitio Lasip only)
Upgrading of primary lines.

February 11, 2010
Thu
9:00 am - 11:00 am
2 hr
Dagupan City: Bonuan Boquig (Pasiliao St., San Gabriel St., Bisal St.,
Bonuan Longos, and Sitio Watak)
Primary line extensions.

February 13, 2010
Sat
5:00 am - 8:00 am
3 hr
Dagupan City: Perez Blvd., Galvan St., Nueva St., Fernandez St.,
(portion only), Burgos St. (portion only), and Gomez St. (portion
only)
Primary line extensions.

February 13, 2010
Sat
5:00 am - 12:00 nn
7 hr
Dagupan City: Rizal St. ext..
Primary line extensions.

February 17, 2010
Wed
9:00 am - 5:00 pm
8 hr
Calasiao: Mancup (Sitio Lasip Boquig only)
Primary line extensions.

February 19, 2010
9:00 am - 5:00 pm
8 hr
Calasiao: Mancup (Sitio Lasip Boquig only)
Primary line extensions.

February 19, 2010
Fri
8:00 am - 12:00 nn
4 hr
1:00 pm - 5:00 pm
4 hr
Dagupan City: Bonuan Sabangan
Upgrading of primary lines.

February 20, 2010
Sat
8:00 am - 12:00 nn
4 hr
Dagupan City: Bonuan Gueset (Villa Milagrosa only)
Upgrading of primary lines.

February 20, 2010
Sat
8:00 am - 4:00 pm
8 hr
Dagupan City: Rizal St. ext. (portion only)
Primary line revamp.

February 24, 2010
Wed
9:00 am - 5:00 pm
8 hr
Calasiao: Mancup (Sitio Lasip Boquig only)
Primary line extensions.

February 26, 2010
Fri
8:00 am - 12:00 pm
4 hr
Dagupan City: Bonuan Gueset (Purok Pagkakaisa only)
Line maintence (washing of insulators)

February 26, 2010
Fri
1:00 pm - 5:00 pm
4 hr
Dagupan City: Bonuan Binloc (La Playa Azul subdivision only)
Line maintenance (washing of insulators)

February 27, 2010
Sat
4:00 am - 9:00 am
5 hr
Dagupan City: Mayombo (portion only), Perez Market site, Rizal St.,
fernandez St. (portion only), Rivera St., Zamora St. (portion only),
Malued, Perez Blvd. (portion only), Tapuac, Poblacion West (Careenan
St. only), Burgos St. (portion only), A.B. Fernandez Ave. (portion
only), A.B. Fernandez West, Carael, Calmay, Lomboy, Salapingao, and
Pugaro Suit.
Primary line extensions.

March 3, 2010
Wed
9:00 am - 12:00 nn
3 hr
Calasiao: Mancup (Sitio Lasip Boquig only) and Lasip (Sitio Lasip Utel
only)
Primary line extensions.

March 4, 2010
Thu
2:00 pm - 3:00 pm
1 hr
San Fabian: Sagud-Bahley (Primicias road portion only and Dispo St.)
Primary line extensions.

March 6, 2010
Sat
8:00 am - 9:00 am
1 hr
Dagupan City:
Rizal St. ext. only
Primary line revamp.

March 10, 2010
Wed
9:00 am - 3:00 pm
6 hr
Sta. Barbara: Nilombot (portion only), Banzal, Erfe, and Leet (phase 3
only)
Primary line extensions.

March 10, 2010
Wed
1:00 pm - 5:00 pm
4 hr
Sta. Barbara: Maningding old road only
Primary line revamp.

March 13, 2010
Sat
8:00 am - 10:00 am
2 hr
Dagupan City: Pantal (Sitio Guibang only)
Primary line extensions.

March 18, 2010 
Thu
8:00 am - 10:00 am
2 hr
Calasiao: Doyong (ortion only)
San Carlos City: Cruz and Bolingit
Primary line extensions.

March 18, 2010
Thu
1:00 pm - 5:00 pm
4 hr
Sta. Barbara: Minien West (portion only)
Primary line revamp

March 19, 2010
Fri
5:00 am - 9:00 am
4 hr
Dagupan City: Mayombo (portion only), Perez Market site, Rizal St.,
Fernandez St. (portion only), Rivera St., Zamora St. (portion only),
Burgos St. (portion only), A.B. Fernandez Ave. (portion only),
A.B. Fernandez West, Carael, Calmay, Lomboy, Salapingao, and Pugaro
Suit
Primary line revamp

March 19, 2010
Fri
8:00 am - 12:00 nn
4 hr
San Fabian: Nibaliw Vidal and Nibaliw Magliba
Line maintenance (Washing of insulators)

March 19, 2010
Fri
1:00 pm - 5:00 pm
4 hr
San Fabian:
Brgy. Nibaliw Vidal (Center Beach only)
Line maintenance (Washing of insulators)

March 30, 2010
Tue
8:00 am - 6:00 pm
10 hr
Dagupan City, Calasiao, and Sta. Barbara: All areas
San Carlos: Cruz and Bolingit
Interruption by National Grid Corporation of the Philippines (NGCP)
for the annual preventive maintenance of its 100 MVA transformer and
associated equipment at Labrador Substation. Including also the
rehabilitation of 69 kV Labrador-Calasiao subtransmission line.

April 8, 2010
Thu
9:00 am - 5:00 pm
8 hr
Calasiao: Buenlag (Merryland Subdivision only)
Primary line revamp.

April 10, 2010
Sat
9:00 am - 12:00 nn
3 hr
Calasiao: Doyong (portion only)
Primary line revamp.

April 14, 2010
Wed
9:00 am - 4:00 pm
7 hr
San Fabian: Sagud-Bahley (Ulanday St. only)
Primary line revamp.

April 21, 2010
Wed
9:00 am - 11:00 am
2 hr
San Fabian: Sagud-Bahley, Nibaliw Central, Nibaliw Magliba, Nibaliw
Narvarte, and Nibaliw Vidal
Primary line revamp.

April 21, 2010
Wed
9:00 am - 5:00 pm
8 hr
San Fabian: Sagud-Bahley (Dispo St., and Ulanday St. only)
Primary line revamp.

April 29, 2010
Thur
7:00 am - 6:00 pm
11 hr
San Jacinto, Manaoag, and San Fabian: All areas
Interruption by NGCP for the annual Preventive Maintenance of 100 MVA
power transformer and associated equipment.

May 4, 2010
Tue
6:00 am - 7:00 am
1 hr
San Jacinto: Sta. Maria, Imelda, and San Roque
Upgrading of primary lines.

May 14, 2010
Fri
8:00 am - 12:00 noon
4 hr
Dagupan City: Pantal
Primary line revamp.

May 15, 2010
Sat
6:00 am - 7:00 am
1 hr
Dagupan City: Mayombo (portion only), Perez Market site, Rizal St.,
Fernandez St. (portion only), Rivera St., Zamora St. (portion only),
Burgos St. (portion only), and A.B. Fernandez Ave. (portion only)
Primary line revamp.

May 15, 2010
Sat
6:00 am - 11:00 am
5 hr
Dagupan City: A.B. Fernandez West, Carael, Calmay, Lomboy, Salapingao,
and Pugaro Suit
Primary line revamp.

May 25, 2010
Tue
7:00 am - 7:15 am
15 min
Dagupan City, Calasiao, and Sta. Barbara: All areas
Energization of DECORP new 69 kV line serving Dagupan substation

May 26, 2010
Wed
6:30 am - 7:00 am
30 min
Dagupan City: Mayombo (portion only), Perez Market site, Rizal St.,
Fernandez St. (portion only), Rivera St., Zamora St. (portion only),
Burgos St. (portion only), and A.B. Fernandez Ave. (portion only)
A.B. Fernandez West, Carael, Calmay, Lomboy, Salapingao, and Pugaro
Suit
Primary line revamp.

June 1, 2010
Tue
7:00 am - 7:15 am
15 min
4:45 pm - 5:00 pm
15 min
San Jacinto, Manaoag, and San Fabian: All areas
Interruption by NGCP to facilitate replacement of rotten wood poles,
crossarms, broken/leaky insulators and correction of overhead ground
(OHGW) and attachments.
				   
June 1, 2010
Tue
8:00 am - 5:00 pm
9 hr
Sta. Barabara: Minien West (Villa Lopez), Sitio Damam, and Wedgewood
heights subdivision
Primary line revamp.

June 2, 2010
Wed
10:00 am - 11:00 am
1 hr
Dagupan City: Manguin (portion only)
Primary line revamp.

June 2, 2010
Wed
1:00 pm - 3:00 pm
2 hr
Dagupan City: Bonuan Gueset (Calamiong only)
Primary line revamp.

June 3, 2010
Thu
9:00 am - 5:00 pm
8 hr
Sta. Barbara: Minien West (Villa Lopez, Sitio Damam, and Wedgewood
heights subdivision only)
Primary line revamp

June 3, 2010
Thu
1:00 pm - 4:00 pm
3 hr
San Fabian: Cayanga (Mckinley St. only)
Primary line revamp.

June 15, 2010
Tue
9:00 am - 5:00 pm
8 hr
Sta. Barbara: Poblacion Sur (Taga-ilog St. only)
Primary line revamp.

June 17, 2010
Thu
9:00 am - 5:00 pm
8 hr
Sta. Barbara: Poblacion Sur (Taga-ilog St. only)
Primary line revamp.

June 23, 2010
Wed
9:00 am - 4:00 pm
7 hr
San Jacinto: Lobong East (portion only) and Labney
Primary line extensions.

June 25, 2010
Fri
8:00 am - 4:30 pm
8.5 hr
San Fabian: Bolasi (PTA resort only)
Primary line revamp.

July 7, 2010
Wed
6:00 am - 8:00 am
2 hr
Calasiao: San Miguel (portion only), Gabon (portion only), Poblacion
East (Pandayan only), Talibaew, Mancup, Buenlag, Macabito, Malabago,
and Doyong
San Carlos City: Cruz and Bolingit
Replacement of rotten pole.

July 7, 2010
Wed
6:00 am - 10:00 am
4 hr
Calasiao: Nagsaing
Primary line extensions.

July 9, 2010
Fri
8:30 am - 12:00 nn
3.5 hr
San Fabian: Bolasi (portion near PTA beach resort only)
Primary line revamp.

July 15, 2010
Thu
6:00 am - 8:00 am
2 hr
Dagupan, Calasiao, and Sta. Barbara: All areas
Interruption by NGCP to correct various 230 and 69 kV hotspots at
Labrador Substation.

July 20, 2010
Tue
9:00 am - 2:00 pm
5 hr
Manaoag: Lelemaan and Inamotan (portion only)
Primary line extensions.

July 22, 2010
Thu
9:00 am - 11:00 am
2 hr
Dagupan City: Arellano St. (Dior Village only)
Replacement of rotten pole.

July 27, 2010
Tue
8:00 am - 12:00 nn
3 hr
Calasiao: Doyong (Sitio Camangaan and Sitio Banaoang)
Primary line extensions.

July 30, 2010
Fri
8:30 am - 3:00 pm
6.5 hr
San Jacinto: Lobong (Sitio Buyan only) and San Juan.
Primary line revamp.

August 4, 2010
Wed
8:00 am - 12:00 nn
4 hr
Dagupan City: Lasip Chico
Primary line extensions.

August 6, 2010
Fri
8:30 am - 3:30 pm
7 hr
San Jacinto: Lobong (Sitio Buyan only) and San Juan
Primary line revamp.

August 12, 2010
Thu
8:30 am - 3:30 pm
7 hr
Sta. Barbara: Matic-matic (core shelter only)
Replacement of rotten pole.

August 12, 2010
9:00 am -11:00 am
2 hr
Sta. Barbara: Minien East (Wedgewood Subdivision and Hills of Wedgewood
Subdivision only)
Primary line extensions.

August 12, 2010
9:00 am - 5:00 pm
8 hr
Sta. Barbara: Minien East (Hills of Wedgewood Subdivision only)
Primary line extensions.

August 13, 2010
Fri
9:00 am - 11:00 am
2 hr
Dagupan City: Pugaro
Upgrading of primary line.

August 24, 2010
Tue
8:00 am - 12:00 nn
4 hr
Dagupan City: Lasip Chico only
Primary line revamp.

August 27, 2010
Fri
8:00 am - 12:00 nn
4 hr
Dagupan City: Bonuan Boquig (Pasilao St., San Gabriel St., Sta. Maria
St., Bisal St., Bonuan Longos, and Sito Watak)
Replacement of broken pole.

August 28, 2010
Sat
4:00 am - 7:00 am
3 hr
Dagupan City: Perez Blvd. (portion only)
Primary line revamp.

September 7, 2010
8:00 am - 6:00 pm
10 hr
Dagupan City, Calasiao, and Sta. Barbara: All areas
San Carlos: Cruz and Bolingit
Interruption by National Grid Corporation of the Philippines (NGCP) to
conduct rehabilitation of Labrador-Binmaley-Calasiao 69 kV line.

September 17, 2010
Fri
8:00 am - 12:00 nn
4 hr
Calasiao: Quesban
Sta. Barbara: Alibago (portion only)
Primary line revamp.

September 17, 2010
Fri
8:30 am - 4:30 pm
8 hr
Sta. Barbara: Payas (portion only) and Carusocan.
Primary line revamp.

September 23, 2010
Thu
8:30 am - 4:00 pm
7.5 hr
Sta. Barbara: Poblacion Norte (portion only) and Dalongue
Replacement of rotten pole.

September 25, 2010
Sat
8:00 am - 12:nn
4 hr
Dagupan City: Pantal (portion only), Sitio Guibang, and Sitio Calima.
Upgrading of primary line.

September 28, 2010
Tue
8:00 am - 12:00 nn
4 hr
Manaoag: Cabanbanan (Sitio Borac only)
Primary line revamp.

September 29, 2010
Wed
8:00 am - 4:00 pm
8 hr
Sta. Barbara: Poblacion Norte (portion only) and Dalongue.
Primary line revamp.

September 30, 2010
Thu
9:00 am - 12:00 nn
3 hr
Calasiao: Buenlag ( Sitio Lasip only)
Primary line revamp.

October 2, 2010
Sat
5:00 am - 6:00 am
1 hr
Dagupan City: Caranglaan, Bacayao Norte, Mayombo, MH del Pilar
St. (portion only), and Arellano St. (portion only).
Primary line revamp.

October 2, 2010
Sat
5:00 am - 11:00 am
6 hr
Dagupan City: Mayombo (portion only from DBP to PNR site).
Primary line revamp

October 5, 2010
Tue
8:00 am - 4:00 pm
8 hr
Manaoag: Cabanbanan (Sitio Borac only)
Primary line revamp.

October 6, 2010
Wed
8:30 am - 3:30 pm
7 hr
Sta. Barbara
Balingueo (BLISS only)
Primary line revamp.

October 7, 2010
Thu
8:00 am - 4:00 pm
8 hr
Manaoag: Cabanbanan (Sitio Borac only)
Primary line revamp.

October 9, 2010
Sat
4:00 am - 8:00 am
4 hr
Dagupan City: A.B. Fernandez East, Tambac (portion only), Arellano St.,
Pantal (portion only), Herrero St., Perez Blvd., Rizal St. ext.,
Rizal St. (portion only), Galvan St., Fernandez St. (portion only),
Burgos St. (portion only), Gomez St. (portion only), Mayombo (portion
only), and Perez Market site.
Primary line revamp.

October 13, 2010
Wed
6:00 am - 7:00 am
1 hr
San Jacinto, Manaoag, and San Fabian: All areas
Interruption by National Grid Corporation of the Philippines (NGCP) to
facilitate Blacksart Service Testing of San Roque HEPP to Concepcion
S/S.

October 13, 2010
Wed
7:00 am - 10:00 am
3 hr
San Fabian: Sagud-Bahley, Nibaliw Central, Nibaliw Magliba, Nibaliw
Narvarte, and Nibaliw Vidal.
Primary line revamp.

October 13, 2010
Wed
8:00 am - 4:00 pm
8 hr
Manaoag: Cabanbanan (Sitio Borac only)
Primary line revamp.

October 15, 2010
8:30 am - 4:00 pm
7.5 hr
Manaoag: Lelemaan (Sitio Dos, Sitio Tres, and Sitio Cuatro)
Primary line revamp.

October 29, 2010
8:00 am - 8:15 am
15 min
4:45 pm - 5:00 pm
15 min
San Jacinto, Manaoag, and San Fabian: All areas
Interruption by National Grid Corporation of the Philippines (NGCP) to
facilitate investigation on unresettable alarm on conservator oil
level of 5 MVA Power Transformer at Bari, Mangaldan.

November 10, 2010
Wed
1:00 pm - 4:00 pm
3 hr
Manaoag: Lelemaan (Sitio Tres only)
Primary line revamp.

November 12, 2010
Fri
8:30 am - 4:00 pm
7.5 hr
Sta. Barbara: Balingueo (BLISS only)
Primary line revamp.

November 12, 2010
Fri
1:00 pm - 4:00 pm
3 hr
Calasiao: Macabito (Sitio Ano only)
Primary line extensions.

November 13, 2010
Sat
8:30 am - 4:30 pm
8 hr
Manaoag: Sta Ines
Primary line revamp.

November 13, 2010
Sat
7:00 am - 12:00 nn
5 hr
Calasiao: Bued (portion only), Quesban, and Gabon.
Sta. Barbara: Alibago (portion only)
Primary line revamp.

November 13, 2010
Sat
1:00 pm - 4:00 pm
3 hr
Manaoag: Baguinay
Primary line revamp.

November 17, 2010
Wed
8:30 am - 4:30 pm
8 hr
Manaoag: Sta. Ines
Primary line revamp.

November 19, 2010
Fri
8:30 - 4:00 pm
7.5 hr
Sta. Barbara: Patayak and Cablong
Primary line revamp.

November 20, 2010
Sat
7:00 am - 12:00 nn
5 hr
Sta. Barbara: Tebag (portion only), Minien West, Leet (portion only),
and Minien East.
Primary line revamp.

November 27, 2010
Sat
7:00 am - 8:00 am
1 hr
11:00 am - 12:00 nn
1 hr
Manaoag: Babasit (portion only), Soriano St., Baritao, Pantal, San
Ramon, Mermer, Tebuel, Licsi, Nalsian, Cabanbanan, Oraan West, Oraan
East, Sta. Ines, Lelemaan, Inamotan, Baguinay, Matolong, and Parian
Primary line revamp.

November 27, 2010
Sat
7:00 am - 12:00 nn
5 hr
Manaoag: Tiong St. (portion only), Galaban St., and Aquino St.
Primary line revamp.

December 1, 2010
Wed
8:00 am - 12:00 nn
4 hr
Dagupan City: Lucao (Millora only)
Primary line revamp.

December 1, 2010
Wed
1:00 pm - 4:00 pm
3 hr
San Jacinto: Casibong
Primary line revamp.

December 3, 2010
Fri
8:30 pm - 4:00 pm
7.5 hr
Sta. Barbara: Patayak and Cablong
Primary line revamp.

December 4, 2010
Sat
6:00 am - 10:00 am
4 hr
Dagupan City: Caranglaan (portion only), Tebeng, Manguin, Tambac
(portion only), Bolosan, Salisay, and Mamalingling.
Primary line revamp.

December 6, 2010
Mon
6:00 am - 9:00 am
4 hr
San Fabian: Anonang
Primary line revamp.

December 8, 2010
Wed
8:30 am - 4:30 pm
8 hr
Manaoag: Pugaro
Primary line revamp.

December 9, 2010
Thu
8:30 am - 3:00 pm
6.5 hr
San Jacinto: San Roque
Primary line revamp.

December 14, 2010
Tue
6:00 am - 6:00 pm
12 hr
San Jacinto, Manaoag, and San Fabian: All areas
Interruption by National Grid Corporation of the Philippines (NGCP) to
facilitate dismantling of decommissioned 69 kV circuit breaker,
current transformer and bypassing of existing 69 kV bus disconnecting
switch in connection with the installation of 69 kV bus breaker and to
facilitate line maintenance works.

December 23, 2010
Thu
9:00 am - 4:00 am
7 hr
Sta. Barabara: Poblacion Sur (portion only)
Primary line extensions.

December 29, 2010
Wed
6:00 am - 7:00 am
1 hr
Dagupan City, Calasiao, and Sta. Barbara: All areas
San Carlos: Cruz and Bolingit
Interruption by National Grid Corporation of the Philippines (NGCP) to
facilitate critical hotspot corrections on upper terminal pad, phase C
of PCB 57LR4 (92.3 deg C).